Project: Connection
The connection of the ski areas in Špindlerův Mlýn is one of the largest projects in the modern history of Špindlerův Mlýn. Here you will find current information on what awaits us and the entire history of the project.
Current: Construction of the new chairlift begins in spring 2026
What does this mean for skiers?
New heated six-seater chairlift with protective bubble from Leitner Ropeways P1 at Hromovky upper station
In addition, a complete red Přehradní slope will be built along the chairlift route
Opening of the Audi line Přehradní chairlift for skiers in December 2026
Map to view HERE
Schedule of key works for 2026
- Spring 2026 - Start of the Audi line Přehradní chairlift technology, excavations for the lower station and network connection. Excavations for the upper station, deforestation of the route, laying snowmaking on Medvědín and start of work on the road bridge. Modeling of the Přehradní ski slope, surface modifications on P1, installation of technologies in the gas station and excavation over the Elbe.
- By mid-August 2026 - completion of concreting of the foundation and supporting structures of the stations and chairlift supports, continuation of the installation of the snowmaking system on the Lesní ski slope and preparation of the P1 terminal.
- August 2026 - completion of the installation of the supports of the new six-seater Audi Line Přehradní chairlift.
- August 18–19, 2026 - installation of the steel structure of the second bridge over road II/295 in the area of the Lesní ski slope arrival.
- Autumn 2026 – assembly of the chairlift technology, installation of the rope, completion of the upper and lower stations, completion of the snowmaking system and final landscaping.
- December 2026 – planned commissioning of the first stage of the project, including the new Audi Line Přehradní chairlift and ski connection via new bridge structures and downhill runs.
- April 2027 – start of construction of the connecting ten-passenger cable car from terminal P1 to Medvědín, the completion of which is planned for the winter season 2027/28. The cable car will complete the complete bidirectional connection of both areas.